Project Overview
This engagement delivered a risk-free, staged upgrade path from Dolibarr v12 to v18 while safeguarding production data and migrating every customization into the supported /custom/ structure. The upgrade followed a strict “Backup First — Staging Only — Future-Proofed” methodology to eliminate downtime and simplify future maintenance.
Core Principles
- Backup First — Full recovery options at every step (database + filesystem + off-site retention).
- Staging Only — All work performed on a private clone with zero production impact until go-live.
- Future-Proofed — All custom code migrated into
/custom/so future Dolibarr upgrades are seamless.
Step-by-Step Plan (Executed)
1. Assessment & Full Backup (Days 1–2)
- Confirmed compatibility (PHP 8.1+, MySQL/MariaDB 10.5+).
- Created complete backups:
mysqldumpdatabase export, full filesystem archive includingconf.php,documents/, and all custom code. - Stored backups securely off-site with 30-day retention.
- Performed a customization audit to locate modifications in core, external folders, and existing
/custom/.
2. Staging Setup & Upgrade (Days 3–5)
- Cloned production into a private staging server.
- Downloaded and installed Dolibarr v18.0.x on staging.
- Merged files carefully: replaced core, preserved
conf.php,documents/, and custom code. - Ran the official upgrade wizard (
/install/) and verified database migration. - Performed initial validation: user login, core modules, and navigation checks.
3. Customization Migration & Testing (Days 6–14)
- Preserved existing
/custom/content; refactored any customizations found in core files or external folders and relocated them into/custom/modules/,/custom/pdf/, etc. - Updated third-party modules to v18-compatible versions.
- Executed rigorous testing:
- Replicated all client workflows (as shown in the provided video).
- Performed end-to-end UAT with the client’s key users via shared staging access.
- Logged, fixed, and documented all issues.
4. Production Go-Live (Days 15–18)
- Scheduled a 30–60 minute off-peak maintenance window.
- Applied upgrade and customization migration on production.
- Cleared caches, locked the installer, and monitored logs for anomalies.
- Delivered updated documentation, a 1-hour training session, and provided 1-week post-launch support.
Timeline & Deliverables
| Week | Focus | Key Deliverables |
|---|---|---|
| Week 1 | Backup, Audit, Staging Setup, Initial Upgrade | Full backups, staging clone, v18 install, initial validation |
| Week 2 | Customization Migration, Module Updates, Testing | Refactored custom code into /custom/, module compatibility, UAT |
| Week 3 | Final Testing, Client Validation, Production Go-Live | Production upgrade, handover docs, training, 1-week support |
Total duration: ~3 weeks (starts upon approval and access). Weekly status updates provided via email or call.
Included & Excluded
Includes
- Full backup & recovery plan
- Staging + production upgrade to Dolibarr v18
- Customization audit, migration into
/custom/, and future-proofing - Third-party module updates (compatibility upgrades)
- Comprehensive testing, deployment, training, and 1-week support
Excludes
- Staging hosting costs (if required; estimated ~$50/month, billed separately)
- Third-party module license fees
Why CnEL India Is the Best Team for This Upgrade
- Proven Dolibarr expertise: Deep hands-on experience upgrading multiple Dolibarr installations across versions while preserving complex customizations.
- Risk-first approach: We prioritize backups, staging, and automated rollback points so your production environment never experiences downtime or data loss.
- Customization-first mentality: We don’t patch core files — we extract, refactor, and migrate your custom logic into the supported
/custom/structure so future upgrades are painless. - Thorough QA & client collaboration: We run real workflows on staging with your team, document every fix, and keep transparent status updates throughout the project.
- Clear handover & support: We deliver documentation, a training session, and a one-week hypercare period so your users transition smoothly.
- Timely delivery: A concise 3-week timeline with defined milestones keeps the project predictable and accountable.
- Security & compliance-minded: Backups, secure off-site storage, and careful credentials handling are standard practice.
Future-Proofing Guarantee
All customizations will be consolidated into /custom/. Following this migration:
- Future minor and major upgrades (e.g., v18 → v19) will be automated and low-risk.
- You may use Dolibarr’s standard update system for security patches and minor releases.
- We provide documentation that makes ongoing maintenance straightforward for your internal team or any future vendor.
Client Testimonial
“CnEL India’s team executed our Dolibarr upgrade flawlessly — zero downtime, no data loss, and every custom workflow preserved. Their staged approach and clear communication made the whole process stress-free. The training and documentation were excellent, and their post-launch support gave our team confidence the moment we went live.”
Next Steps
To proceed, please confirm and provide:
- Production server access (SFTP + DB credentials)
- List of key users for staging testing
- Preferred start date
We are ready to begin as soon as access is provided. For scheduling or questions, contact us and we’ll finalize the kickoff call and milestones.